WD Overhaul Update 2016 December 2

The first Photo is the piston valve cylinder with the lining removed. The new linings are currently being machined at Rileys of Bury and following this will be installed, being shrunk with liquid nitrogen to form an "expansion fit".


The other two show the progress of the boiler fittings and the cladding.


Photos Courtesy of Neil Sharpe & Bryan Toovey